E180th Sewer & Water Main
Bronx, NY
Monadnock Construction - Work on this project included the installation of upgraded sewer and water mains in the street and sidewalks. To progress the work offsets in the water main were provided to reduce hand excavation near existing street trees. Underground electric oil-o-static lines were supported while rock was excavated and the new sewer main was installed. Complicating this installation was a difficult traffic management plan due to a major bus depot being located nearby.